Entering Resource Information in Microsoft Project

While we've entered a number of tasks and set the predecessors for these tasks, we haven't yet assigned resources to the individual tasks of the project. Before we can assign tasks to resources, we need to first create those resources that will be responsible for completing the work. Microsoft Project allows you to enter tasks without resources being associated with them since in most instances, you will not know who will actually be doing a specific task until later in the project.

To switch to the screen used to creating new resources, click on the 'Resource Sheet' from the left-hand side toolbar. Your screen will look similar to the one below. Again there are two ways to enter resources into Microsoft Project. You can use the resource spreadsheet of the resource sheet or you could use the Resource Information dialog. We'll cover both methods of entering resources into Project.

Note: If you create a resource and assign that resource to a task, the resource can not be deleted from the project until all task associated with the resource have been reassigned to another resource.

enter resource info

 

 

< Project Management Terms Defined Creating Resources with Spreadsheet >

 The Principles Of Project Management - Free 66 Page Preview!: Every project you manage will be unique. Scope, budgets, team dynamics, and timeframes will differ. As a project manager, the most important factor in achieving project success will be your understanding of 'The Principles Of Project Management'. This book will show you that project management isn't rocket science.

Outsourcing Web Projects: 6 Steps to a Smarter Business - Free Preview!: Outsourcing Web Projects: 6 Steps to a Smarter Business provides you with tried and tested techniques that will ensure that you can deliver complex, high quality web projects using outsourced development resource, both on time and on budget!